DHHL Project Work To Impact Waimea Traffic

Posted on Nov 5, 2013 in Department of Hawaiian Home Lands, Media Releases

Hawaii State Seal
NEWS RELEASE

Nov. 5, 2013

DHHL Project Work To Impact Waimea Traffic

WAIMEA, HAWAI‘I – The State Department of Hawaiian Home Lands is advising the Waimea community and motorists of plans to begin work on Kawaihae Road Improvements at South Kōhala Distribution Road in the vicinity of Lālāmilo Housing Phase 2A, Increment 1.

DHHL Contractor Goodfellow Bros., Inc. (GBI) is planning to begin construction in mid-November on the South Kōhala Distribution Road (SKDR) and on the SKDR/Kawaihae Road intersection. GBI currently plans to close one lane during construction on South Kōhala Distribution Road, and one lane during construction on Kawaihae Road.

Project work will be performed in two phases:

Phase 1 will begin shortly and last for four weeks. During this phase, work will be done to install water facilities and improvements, including water lines, manholes, boxes, and meters in the area. Work will impact both Kawaihae Road and South Kōhala Distribution Road. The majority of the work will be on South Kōhala Distribution Road and includes two nights of work in the Kawaihae Road/SKDR intersection. Water shut-off will also be required on two nights during the Kawaihae Road/SKDR intersection work.

Phase 2 will last 12 weeks. Work on this phase includes grading, paving, and constructing drainage and other roadway improvements. Work will impact both Kawaihae Road and South Kōhala Distribution Road.

Construction on these phases of the project will extend from mid Nov. 2013 to the end of Mar. 2014. Total construction time of this work is estimated at 16 weeks.

A project information sheet is attached with further information and maps of the project area.

DHHL Project Manager:
Jeffrey Fujimoto
(808) 620-9274
[email protected]

# # #

Media Contact:
Punialoha Chee
Public Information Officer
(808) 620-9591
[email protected]